Editor’s note: This is a schedule of work being planned for Oct. 11-16. Weather conditions and unforeseen problems can cause delays or cancellation of work.

Bowie County

I-30 – From FM 989 to Arkansas State Line, widening highway. Construction work will begin on shoulders with most of the work being conducted at night.

Texas 8 – At Sulphur River, replacing bridges.

Texas 93 – U.S. 82 and U.S. 67, installing sidewalks.

Texas 8 – At Anderson Creek, replacing bridge. All traffic restricted to one lane with signal lights controlling traffic through work zone.

Camp County

None

Cass County

Texas 8 – At Sulphur River, replacing bridges.

Harrison County

U.S. 59 – From FM 1997 to Marion County line, repairing and resurfacing highway. Traffic restricted to one-lane each direction.

Texas 43 – From Loop 390 to Haggerty Creek, repairing and resurfacing highway.

FM 1186 – From U.S. 59 to Panola County line, installing safety end treatments on culverts.

Marion County

U.S. 59 – From 1.5 miles south of FM 2208 to Harrison County line, repairing and resurfacing highway. Traffic restricted to one-lane each direction.

Morris County

Texas 49 – From Titus County line to FM 144, repairing and resurfacing highway.

Panola County

U.S. 79 – From Texas 149 to Rusk County line, repairing and resurfacing highway.

U.S. 59 (NE Loop) – From U.S. 59 North to U.S. 79 East, repairing and resurfacing highway.

Titus County

Texas 49 – From FM 1735 to Morris County line, repairing and resurfacing highway.

Upshur County

None

Tags